Carroll Hospice Dove House, Phase I Renovations

Healthcare

Phase 1 of the interior renovations at Carroll Hospice Dove House consisted of adding 7 guest rooms with bathrooms and renovating a reception area, office space, and a nurse’s station, all while being occupied in the existing guest patient wing. This first phase included new finishes, millwork, mechanical, electrical, and plumbing work. The second phase involved the renovation of the existing building entry, lobby area, and an adjacent guest room to create a wider lobby area, new nurse’s station, copy room and med room. Finishes were upgraded in the offices, conference room, and chapel. The third phase included renovating the old nurse’s station into a storage room, consisting of new finishes and shelving.

Logistics, scheduling, and phasing were all very critical given the nature of the facility and that it operates 24 hours a day.

Project Photos

Project Location


What Can We Build For You?

Become a valued client

Let's Build Together

Become a trusted subcontractor

Top 4 Reasons to Join Our Team

According to the team!